Proposed Fort Bliss data center could use more power than all of El Paso

Army wants Fort Bliss data center in far East El Paso to be operational by 2027.

By Diego Mendoza-Moyers, El Paso MattersMay 7, 2026 9:30 am, ,

From El Paso Matters:

The U.S. Army is proposing developing a gargantuan, 3-gigawatt data center complex on Fort Bliss property that within a few years would consume more electricity than all of El Paso Electric’s 460,000 customers combined – even as questions about its development, water usage and air pollution remain unanswered.

If built, it would be the third major data center project in the El Paso region, along with Meta Platform’s $10 billion facility in Northeast and the $165 billion Project Jupiter campus that Oracle and OpenAI are building in Santa Teresa, New Mexico. The combined scale and size of the three facilities could quickly transform the Borderland into one of the nation’s core hubs of power generation and AI infrastructure.

The publicly-traded investment firm Carlyle Group would pay to build and operate the Fort Bliss data center – one of several planned in a national rollout under President Donald Trump’s administration to rapidly increase artificial intelligence technology for the Department of Defense.

At Fort Bliss, the Army is “targeting an initial operating capacity of about 100 megawatts on the compute side” by next year, David Fitzgerald, deputy undersecretary of the Army, said during a meeting with reporters April 22. An official estimated cost for the project has yet to be released.

It’s also not clear how the project could replace the same amount of water that it consumes.

It’s possible the Kay Bailey Hutchison Desalination Plant – co-owned by El Paso Water and the U.S. Army – could play a role in making the data center water neutral. But El Paso Water said it has no details about how the data center facility could achieve water neutrality.

El Paso Water is “more than willing to continue to share ideas for best practices in sustainability to help protect our regional water resources,” the utility said in its statement.

As far as electricity generation, Army officials said they don’t know if El Paso Electric would build a new power plant to serve the data center. It’s also possible that Carlyle Group or another private company could build its own power generation source for the data center that’s isolated from the power grid El Pasoans use every day.

“We have to decide whether El Paso Electric is going to be the ones building whatever is coming, or if this is going to be some independent power producer,” Waksman said.

El Paso Electric is planning to develop a 366 megawatt power plant made up of over 800 small gas generators to power Meta’s data center. The utility will build more generation in the coming years to meet 1 gigawatt of total demand from Meta’s facility. Meanwhile, as the technology giant Oracle develops Project Jupiter, the company said Monday it is seeking to power the campus using 2.45 gigawatts of fuel cell power systems provided by the company Bloom Energy.

For perspective, 3.45 gigawatts – the combined projected demand of those two major data centers – is enough electricity to power as many as a million homes, depending on the time of day and weather.

The Fort Bliss project would have to meet environmental regulatory requirements, and the developer needs to include a plan for providing utilities and infrastructure needs such as access to the facility, according to a request for proposals issued by the Army in December 2025. Army officials emphasized the project would not impact El Pasoans’ water or electric bills.

Who is Carlyle Group?

Carlyle Group is a global investment management firm that oversees $477 billion of assets from entities such as pension funds.

The company invests that money by buying businesses ranging from wine producers to Asian telecommunications companies, or by developing infrastructure projects such as renewable energy generation and data centers. The company in 2025 posted distributable earnings of nearly $1.7 billion on $4.8 billion in revenue.

The Army wants to build the facility at Fort Bliss in partnership with Carlyle because the installation has a large amount of available, unused land and because of the water and electricity infrastructure already in place in El Paso, Fitzgerald said.

The Carlyle data center planned for El Paso is part of a wider U.S. military effort to quickly build infrastructure that supports the use of artificial intelligence — both on the battlefield and in running its day-to-day operations, according to government documents.

Army officials nodded to the use of AI in drone warfare and targeting systems. And a hyperscale data center facility can also securely house information such as the military’s cloud database that details pay and entitlements for every U.S. soldier, said Maj. Gen. Curtis Taylor, commanding general of the 1st Armored Division and Fort Bliss.

Data centers are “essential parts of power projection,” Taylor said. “But we have to protect those servers. And that’s why there’s great utility in building that infrastructure on military installations.”

The Fort Bliss facility would be located on a plot of land near the intersection of Loop 375 and Montana Avenue. The site is just east of the Camp East Montana immigrant detention facility, and near El Paso Electric’s gas-fired Montana power station.

The plan is for Carlyle to utilize the majority of the data center’s capacity for its business needs, and the military would have access to a more secure portion of the data center for its own uses.

The Army is developing another similar data center project in Dugway, Utah. Other Army bases identified as potential sites include Fort Hood in Texas and Fort Bragg in North Carolina.

The U.S. Air Force in October issued a solicitation saying it is “accepting proposals for the development of Artificial Intelligence data centers,” on unused land at different bases, including in California, Georgia, Arizona and Tennessee. The push was enabled by executive orders signed by Trump that seek to speed up permitting and development timelines for AI data centers.

Would the Fort Bliss data center pay taxes?

A privately-financed data center on Fort Bliss would likely have to pay some taxes – unlike on-base government facilities – but there’s a lot of uncertainty.

Carlyle Group is leasing the land for the data center under an “enhanced use lease” that allows branches of the military to rent under-used land on bases.

Land on federal installations is not subject to state or local taxes. However, the statute that authorizes the U.S. military to lease excess land to private entities says that “the interest of a lessee of property leased under this section may be taxed by State or local governments.”

So, while the land the data center is built on would not be subject to taxation, the structures housing the data center could be subject to local property taxes.

But it depends on how the deal is structured, including factors such as whether Carlyle or the Army ultimately takes ownership of the buildings.

The Army in January awarded a contract to Korean-owned Hanwha Defense USA, which will invest $1.3 billion to develop a munitions factory at a base in Pine Bluff, Arkansas, using an enhanced use lease.

Fitzgerald, the Army undersecretary, acknowledged the public pushback to other data centers such as Meta and Project Jupiter. But he said the Army wants to ensure the project is developed “the right way.”

“There are always elements that will kind of make this an ‘us versus them’ sort of a construct, but I don’t think we view it that way from the Army,” he said. “I think there’s a path here that will benefit not just the installation, but the community as well.”